The eight year old Mozingo Lake Events Center is getting a $906,166 dollar replacement of its heating and air conditioning (HVAC) system.
Click the LISTEN button to hear comments from the October 12, 2026 Maryville city council meeting.
A presentation at this week's Maryville city council meeting from its outside consultant explained that three of the building's original seven HVAC units are oversized.
That caused high humidity in the lower level of the building that could have resulted in mold.
Presentation materials shown at the meeting said the replacement would result in savings over the next 20 years of more than $167,000 dollars and a future cost avoidance of more than $250,000.
The replacement is scheduled to be completed in July 2027.
Click HERE to read and download background information about the HVAC replacement project.