Work on the Clear Creek Wind Farm project begins

Work on the Clear Creek Wind Farm project begins soon in Nodaway County. The Missouri Department of Transportation and the contractor installing the Clear Creek Wind Farm have contracted with Herzog to resurface and realign portions of roads which will be utilized during the construction of the wind farm.

According to MoDot, beginning today, crews will resurface Route FF, just north of 110th street and Route B. That project should take approximately five working days to complete. Following completion of Route FF, crews will move to Route JJ for approximately seven days and then to Route FF and B between Hallmark Road and Imperial Road for three days.

The entire resurfacing project should be complete by early July.  During that time, crews may close portions of each roadway.