2011-01-05MARYVILLE, MO |  By: Nichols

Streetscape Project

Heartland Brothers from Grandview, Missouri was awarded phase two a 45 day project and Ameno Brothers was awarded phase three a 75 day project. Maryville city manager Matt Lecerf says traffic will be re-routed but will not affect the individuals, clients, or business owners who are located in the areas of the project. Phase two will upgrade the areas of third and Main and 4th and Main Streets in Maryville. Phase three will affect the areas outside the square along 3rd and Main and market, Main and 3rd and 4th, and finally 4th and Main and market. Both projects will begin this Spring.